top of page

Rickmansworth Park JMI School – Hertfordshire

  • Feb 27, 2025
  • 2 min read

Updated: Jul 27

Delivering a Live School Refurbishment Without Disrupting Education


Harvey Electrical was appointed by Ei Projects to deliver the complete electrical installation as part of the refurbishment of Rickmansworth Park JMI School under the Hertfordshire County Council Framework.


Working within a fully operational primary school presented challenges that extended well beyond the electrical installation itself. Every phase of the project required careful planning, stakeholder coordination and flexible programme management to ensure teaching could continue safely whilst the refurbishment progressed.


This project demonstrates Harvey Electrical's ability to deliver complex electrical installations within occupied environments where safety, communication and programme management are just as important as technical expertise.


Rickmansworth JMI School | Classroom
Rickmansworth JMI School | Classroom

The Challenge

Unlike an empty refurbishment, every element of this project had to be carefully planned around the day-to-day operation of a busy school.


Working alongside Ei Projects, Hertfordshire County Council, Building Control and the school leadership team, we developed a phased delivery programme that maintained a safe learning environment throughout the works.


Key challenges included:

  • Maintaining a fully operational school throughout construction.

  • Programming classroom works around teaching timetables.

  • Completing circulation areas during evenings, weekends and school holidays.

  • Managing temporary electrical services during phased changeovers.

  • Maintaining fire alarm protection throughout the refurbishment.

  • Coordinating multiple trades within occupied areas while ensuring the safety of pupils, staff and visitors.


Delivering this level of coordination required detailed forward planning, clear communication and a proactive approach to problem solving.



External View
External View

Harvey Electrical's Solution

Rather than acting solely as the electrical contractor, Harvey Electrical became an integral member of the wider project team, working collaboratively with Ei Projects to ensure every phase was delivered safely, efficiently and on programme.

Our scope included:


Electrical Infrastructure

  • New electrical distribution

  • Containment systems

  • Complete wiring installation

  • Energy-efficient LED lighting

  • Emergency lighting

  • Small power installations


Fire & Life Safety

  • Complete fire alarm replacement

  • Smoke and heat detection upgrades

  • Phased commissioning while maintaining operational fire protection


Technical Coordination

  • Coordination with multiple trades

  • Liaison with Hertfordshire Building Control

  • Phased electrical changeovers

  • Temporary electrical supplies

  • Programme planning and sequencing


Testing & Handover

  • Full inspection and testing

  • NICEIC certification

  • Record drawings

  • O&M manuals

  • Client demonstrations

  • First-year servicing package


Commercial Project Delivery in Action

Projects within live educational environments demand more than technical installation.

They require contractors who understand how to balance construction activities with the ongoing operation of the building.


Throughout the refurbishment, Harvey Electrical worked closely with Ei Projects, Hertfordshire County Council and the school to minimise disruption, maintain compliance and ensure every phase was completed safely and efficiently.


This collaborative approach enabled the refurbishment to progress while allowing the school to continue operating throughout the construction programme.


Live Operational Primary School
Live Operational Primary School

The Outcome


The completed refurbishment has provided Rickmansworth Park JMI School with a modern, compliant and energy-efficient electrical installation designed to support both current teaching requirements and future development.


Most importantly, the project was delivered successfully without disrupting the day-to-day operation of the school, demonstrating Harvey Electrical's ability to deliver complex refurbishments within live occupied environments.



Project Highlights


✔ Live operational primary school

✔ Hertfordshire County Council Framework

✔ Complete electrical refurbishment

✔ Phased programme delivery

✔ Technical coordination with multiple stakeholders

✔ New electrical distribution

✔ LED lighting upgrade

✔ Emergency lighting installation

✔ Complete fire alarm replacement

✔ Testing, commissioning and NICEIC certification

✔ Successful project handover